DPM Metals reaches commercial production at Vareš silver-gold mine in Bosnia and Herzegovina
Reuters2026/08/17 10:45- DPM Metals reached commercial production at the Vareš silver-gold mine in Bosnia and Herzegovina on Aug. 10, 2026.
- Milestone met by sustaining over 60% of design throughput and recoveries for 30 consecutive days.
- Throughput averaged 72% of design capacity during the test period.
- Full run-rate of 850,000 tonnes per year targeted by year-end 2026.
- 2026 output expected at the high end of guidance of 105,000 to 130,000 gold equivalent ounces.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
After seeing the largest weekly inflow since April, Bitcoin ETF turns to a net outflow of $390 million, with institutional sentiment turning bearish again.
Last week, U.S. spot bitcoin ETFs experienced their largest single-week net outflow since the end of June, completely reversing the strong momentum seen at the beginning of August.

Defsec prices private placement at CAD 2.84 per share, targets CAD 5.54 million proceeds
Cosan net debt falls 20% to R$ 9.2 billion in Q2 2026
RCI Hospitality director Eric S. Langan reports purchase of 1,630 common shares for $50,204