TAESA secures installation license for Juruá transmission project in São Paulo state
Reuters2026/08/11 00:03- TAESA secured an installation license from São Paulo environmental regulator CETESB for its Juruá transmission project, clearing construction to start.
- Project is Lot 3 from Brazil’s Transmission Auction 02/2024, fully controlled by TAESA.
- Targets RAP of R$ 20.5 million for the 2026-2027 cycle; ANEEL capex set at R$ 244 million.
- Includes a 1.2 km line section, the 440/138 kV Estância substation in Barra Bonita, São Paulo; energization deadline June 2028.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Goldman Sachs urges investors not to exit! Optimistic outlook supported by three reasons: steady interest rates, falling oil prices, and AI boosting economic resilience
Ashok Varadhan, Co-Head of Goldman Sachs Global Banking & Markets, conveyed a simple message to investors concerned about rising interest rates, high oil prices, and the resilience of the economy—stay invested.

Enjoei announces extraordinary shareholders meeting
Bunker Hill Mining adopts amended by-laws, raises shareholder meeting quorum to 33.33%
Enjoei board proposes 10-for-1 reverse stock split to lift share price above BRL 1