Nexans Completes Subsea Cable Installation for Chevron’s Jansz-Io Project
Bitget2026/11/20 07:19- Nexans completed subsea cable installation and burial for Chevron Australia’s Jansz-Io Compression project in October 2026.
- The 145 kV dynamic cable spans approximately 135 km between Barrow Island and a floating control station.
- Installation included 26 buoyancy modules; 30 km of cable was buried.
- Cable connections and rock placement along the final 28 km remain outstanding before commissioning.
- Chevron Australia plans the final energization test for February 2027.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like

Ethereum co-founder recommends synchronous composability technology

After many years, Apple plans to relaunch its charity collaboration with (RED), introducing special edition HomePod mini 2 and AirPods Max 2.
This will be Apple's first Product(RED) hardware release in over two years since the 2023 Apple Watch Series 9. The HomePod mini 2 will feature a red mesh exterior, with its overall design remaining consistent with the existing version, differing only in color. The AirPods Max 2 will return with a silver body, paired with white mesh ear cushions, a white headband, and a multifunctional control knob in red.