Ferrovial targets October 2027 financial close for I-285 East Express Lanes project
Bitget2026/10/27 21:10- Ferrovial expects commercial close for Atlanta's I-285 East Express Lanes in December 2026, with financial close targeted for October 2027.
- The committed, 23-mile first phase carries $8.9 billion in construction costs, with a proposed concession payment of $23.6 billion.
- Groundbreaking is expected in the first quarter of 2028, with full service scheduled to begin in 2034.
- Two subsequent phases target openings in 2036 and 2040, respectively, under separate agreements within the development framework.
- The developer targets double-digit equity returns, expecting to fund equity commitments without issuing shares at the parent level.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Indonesian Rupiah: External headwinds and MSCI risks – OCBC
Taiwan Dollar: Strong fundamentals but near-term pressure – Commerzbank

Hassett Downplays AI Debt Risk: The Industry Has Sufficient Funds, No Risk of Broad Sell-Off
Kevin Hassett, Director of the White House National Economic Council, stated that the recent substantial decline in technology stocks does not indicate a comprehensive sell-off risk for the AI industry. He acknowledged that some enterprises are indeed burdened with significant debt, which warrants attention. However, he also pointed out that there are many financially strong companies within the industry that hold both equity and debt in related firms; these companies may be poised to acquire or provide funding support when opportunities arise.